To assure a quality product, the contractor will complete the milling and resurfacing of Iowa 12/Riverside Boulevard in the spring of 2021. With additional time required to complete underground utility replacement and the cool fall temperatures, it has been determined to be the best course of action. The contractor would restart operations the first week of May 2021, weather permitting. The milling and paving operation is anticipated to take three to four weeks, with project completion June 2021.

Knife River Midwest was awarded the $2.1 million project.